Should we sell our clean power to AI data centres?

The debate is framed as for or against AI. That is the wrong question. A data centre is a machine that turns electricity into computing. The question is what we get per megawatt, and who pays for the grid.

876
homes' worth of power in one megawatt running all year (est.) est.1
150
permanent staff at the top of the typical 25-to-150 range for a million-square-foot data centre R2

Both are true. They answer different questions.

A compositeA town council in the Interior is offered a 400 MW campus. That is power for about 876 homes per megawatt, so roughly a city's worth of electricity. The pitch promises construction crews. The permanent payroll fits in one office floor.
Before you scroll · take a guess

Ireland let data centres grow fast. What share of the country's electricity did they use by 2023?

Start with the good news

Stop 2 · The twist

The same data centre can be a great deal or a bad one

Flip it. The toggle is the argument.

Brings its own power

The operator pays for new clean supply and the wires it needs. Your bill barely moves. The clean grid stays clean.

Draws on ours

The load takes existing clean power. Gas or imports fill the gap. Grid upgrades get spread across every household.

Canada has more than 10R4 GW of proposed capacity in some stage of the pipeline, and Alberta alone has over 30R5 AI projects queued. Ireland's answer was to require big sites to provide their own generation or storage.8 In the U.S., utilities have filed record rate increases tied partly to data centre load.9

Stop 3 · The fix

Your turn: write the deal

Three terms decide most of the outcome. A large-load tariff makes the data centre pay for the grid it needs.10 The model counts totals, not your bill: how those costs split across ratepayers depends on the utility.

Illustrative model, not measured data
Bigger brings more investment, and more risk of building for demand that never shows up.
Tougher terms send some projects to Alberta or the U.S.
Protects households. Raises the operator's costs.
—homes' worth of power
—grid cost left on ratepayers a year
—existing clean power drawn away a year
—emissions if gas fills the gap a year

Two readings

Camp 1: build it here

Clean power is our edge. If we don't host AI computing, another country will, likely on dirtier power, and we lose the investment and the tax base.

If they are right: deals with tough terms still attract projects.

Camp 2: protect the grid

Clean power is scarce, and LNG, mines and electrification all want it. Selling it cheaply to a few hundred jobs is a bad trade.

If they are right: large data centre loads raise household rates or bring back gas.

Our read

Yes, on terms: bring your own clean power, pay your share of the grid, and keep a slice of the computing for Canadian users. Without those, no.

We would change this read if a jurisdiction shows big data centre loads lowering household rates without any of these terms.

What better looks like

  1. A published rate class for large loads, so data centres pay for the grid they need.
  2. An additionality test: new clean supply on the grid before, not after, the load connects.
  3. Public value per megawatt: jobs, tax and Canadian-owned computing for each approved project.

Ask your utility regulator and MLA: "If a data centre connects here, who pays for the grid upgrades, and where does the power come from?"

Stop 4 · Check us

Sources and the data layer

V Verified: confirmed against the primary document cited.
R Reported: credible secondary source; primary pending or not public.
est. Illustrative: our own model or estimate, computed from the figures above. Marked est.
  1. Istari model; grid-cost share and per-home use are stated assumptions, editable here. istaristrategy.com · retrieved 2026-11-21
  2. Brookings, "New evidence on data center employment effects". brookings.edu · retrieved 2026-06-06
  3. Natural Resources Canada, Energy Fact Book (non-emitting share of electricity). natural-resources.canada.ca · retrieved 2026-06-06
  4. Data Center Knowledge, "Canada emerges as global data center powerhouse". datacenterknowledge.com · retrieved 2026-06-06
  5. CBC News, AI data centres in Alberta (queue of projects). cbc.ca · retrieved 2026-06-06
  6. The Narwhal, "B.C. Premier Lorne Doerkson unveils new cabinet, reshuffling key portfolios," Nov 20, 2026 (LNG targets; energy ministry). thenarwhal.ca · retrieved 2026-11-21
  7. National Observer, Apr 14, 2026, Microsoft Ontario data centres: power and water use. nationalobserver.com · retrieved 2026-06-06
  8. Pinsent Masons, Irish regulator rule on data centre power. pinsentmasons.com · retrieved 2026-06-06
  9. Brookings, "Confronting and addressing rising energy bills linked to data centers". brookings.edu · retrieved 2026-06-06
  10. Columbia Sabin Center, "Large-load tariffs and clean transition tariffs," Jun 2, 2026. blogs.law.columbia.edu · retrieved 2026-06-06
  11. IIEA, "Data centres in Ireland: the state of play". iiea.com · retrieved 2026-06-06
Open the data layer: every number on this page
FigureValueTagKeySource or formula
Share of Canada's electricity that is non-emitting82%VerifiedcleanNatural Resources Canada, Energy Fact Book (non-emitting share of electricity)
Permanent staff at a million-square-foot data centre, low25Reportedjobs_loBrookings, "New evidence on data center employment effects"
Permanent staff at a million-square-foot data centre, high150Reportedjobs_hiBrookings, "New evidence on data center employment effects"
Data centres' share of Ireland's electricity, 202321%Verifiedireland_23IIEA, "Data centres in Ireland: the state of play"
Data centres' share of Ireland's electricity, 20155%Verifiedireland_15IIEA, "Data centres in Ireland: the state of play"
AI data centre projects in Alberta's queue30Reportedab_queueCBC News, AI data centres in Alberta (queue of projects)
Canadian data centre capacity across all pipeline stages10Reportedpipeline_gwData Center Knowledge, "Canada emerges as global data center powerhouse"
Platform goal: multiply B.C. LNG output by 20322Reportedlng_xThe Narwhal, "B.C. Premier Lorne Doerkson unveils new cabinet, reshuffling key portfolios," Nov 20, 2026 (LNG targets; energy ministry)
Hours in a year8,760IllustrativehoursIstari model; grid-cost share and per-home use are stated assumptions, editable here
Model: grid cost left on ratepayers we call small$100MIllustrativeok_costIstari model; grid-cost share and per-home use are stated assumptions, editable here
Model: additionality we call strong60%Illustrativeok_addIstari model; grid-cost share and per-home use are stated assumptions, editable here
Model: below this load, the deal is too small to matter either way500Illustrativesmall_mwIstari model; grid-cost share and per-home use are stated assumptions, editable here
Model: electricity a typical home uses in a year10Illustrativemwh_homeIstari model; grid-cost share and per-home use are stated assumptions, editable here
Model: annualized cost of wires and firm capacity per MW of new load (assumption)0.8Illustrativegrid_costIstari model; grid-cost share and per-home use are stated assumptions, editable here
Model: emissions of gas power that backfills the load0.4Illustrativegas_tIstari model; grid-cost share and per-home use are stated assumptions, editable here
Homes powered by one megawatt running all year876Illustrative · est.homes_per_mw= hours/mwh_home
Growth in Ireland's data-centre share, 2015 to 20234.2×Illustrative · est.ireland_x= ireland_23/ireland_15
A note from Istari

You read to the end, which is the job description. If your organization has a question like this sitting in its records, this is what the answer can look like, built from your own data, in weeks. Start the conversation.