ISTARITHINK TANK
Stop 1 · The itch
This weekThe new premier has promised to scrap the Massey tunnel and build a bridge instead. With no fall sitting, cabinet orders could start changing the project now.8

Why do some B.C. projects cost double?

The usual answer is inflation. Inflation is real. Here is how much of the bill it actually explains.

37%
rise in Vancouver construction prices, late 2020 to fall 2026 est.12
105%
rise in the Massey tunnel budget over five years est.34

Both are true. They answer different questions.

A compositeA Ladner kid who started kindergarten in 2022, the year the cancelled bridge was due to open, will be starting Grade 9 when the tunnel now opens in 2031R4.
Before you scroll · take a guess

Construction prices rose about a third. After that inflation, how much did the Broadway Subway budget grow?

Start with the good news

Stop 2 · The twist

Strip out inflation and the list reorders itself

Flip it. The toggle is the argument.

Every project looks like a scandal. Massey is up 105%. Richmond Hospital more than doubled.

Projects signed before the 2021 price spike come in below inflation. Projects still being designed through it blew past it.

$4.15B × (151.4 ÷ 110.7) = $5.7B if only prices had changed
$8.5B − $5.7B = $2.8B inflation does not explainInflation explains about 35% of Massey's increase. No Vancouver index exists for tunnels, so we use the closest local one. Budgets usually include escalation to completion, so this method can understate inflation's share.

The pattern points at one lever: risk is cheapest to lock in early, and most expensive to carry through years of redesign. It shows up on household bills too. The North Shore wastewater plant went from $0.7BR6 to $3.86BR6, 5.5×est.6 the first figure. North Shore households now pay about $590R6 a year for 30 years toward it.

Stop 3 · The fix

Your turn: the bridge, in today's dollars

The cancelled bridge had a $3.5BR7 budget in 2017. Its lowest bid was $2.6BR7. Move it to today's prices, then add what a restart costs. This leaves out what a switch writes off on the tunnel.

Illustrative model, not measured data
The budget was $3.5B. The lowest bid was $2.6B. Which one do you trust?
Every restart repeats engineering and consultation. Nobody publishes this number.
Each year waiting adds a year of construction inflation, assumed at 4% a year.
—bridge cost, your version
—vs the tunnel's $8.5B

Two readings of the switch

Camp 1: the bridge is cheaper

In today's prices the 2017 bridge is about $5.3Best.71, well under the tunnel's $8.5B.

If they are right: a costed bridge business case lands under the tunnel budget.

Camp 2: switching is the expensive part

The projects that blew up were the ones redesigned through the price spike. A restart adds years of exactly that.

If they are right: the bridge's new budget, once published, lands near or above the tunnel's.

Our read

Bridge or tunnel matters less than how fast the choice locks in. The cheapest crossing is the one under a signed contract soonest.

We would change this read if a project redesigned after 2021 comes in at or below construction inflation.

What better looks like

  1. One dashboard: every major project's budget against its first approved baseline, adjusted for construction inflation, updated quarterly.
  2. Restart costs in the open: what B.C. has already spent on the tunnel, and what a switch writes off.
  3. A date to sign: when the bridge goes to contract.

Ask your MLA: "What has the tunnel cost so far, and what will a switch to a bridge write off?"

Stop 4 · Check us

Sources and the data layer

V Verified: confirmed against the primary document cited.
R Reported: credible secondary source; primary pending or not public.
est. Illustrative: our own model or estimate, computed from the figures above. Marked est.
  1. Statistics Canada, The Daily, Jul 30, 2024, building construction price indexes (Vancouver non-residential). www150.statcan.gc.ca · retrieved 2026-10-31
  2. Statistics Canada, The Daily, Oct 29, 2026, building construction price indexes (Vancouver non-residential). www150.statcan.gc.ca · retrieved 2026-10-31
  3. Daily Hive, Aug 18, 2021, Massey tunnel business case. dailyhive.com · retrieved 2026-10-31
  4. Global News, Jul 6, 2026, Massey tunnel cost increase. globalnews.ca · retrieved 2026-10-31
  5. Daily Hive, Dec 18, 2024, Broadway Subway and Pattullo Bridge cost updates. dailyhive.com · retrieved 2026-10-31
  6. CBC News, North Shore Wastewater Treatment Plant cost-sharing decision. amp.cbc.ca · retrieved 2026-10-31
  7. Daily Hive, cancelled 10-lane bridge budget and lowest bid. dailyhive.com · retrieved 2026-10-31
  8. Victoria News, "Incoming B.C. premier Doerkson says there will be no fall legislative session," Nov 16, 2026 (Massey bridge pledge; cabinet orders). vicnews.com · retrieved 2026-11-21
  9. Daily Hive, Jun 4, 2024, Richmond Hospital cost update. dailyhive.com · retrieved 2026-10-31
  10. Daily Hive, Sep 12, 2023, Cloverdale hospital cost. dailyhive.com · retrieved 2026-10-31
  11. Daily Hive, May 21, 2026, Site C final cost. dailyhive.com · retrieved 2026-10-31
  12. Istari model; the restart premium and yearly inflation are the reader's assumptions. istaristrategy.com · retrieved 2026-11-21
Open the data layer: every number on this page
FigureValueTagKeySource or formula
Massey tunnel, business case (Aug 2021)$4.15BReportedmassey_0Daily Hive, Aug 18, 2021, Massey tunnel business case
Massey tunnel, latest budget (Jul 2026)$8.5BReportedmassey_1Global News, Jul 6, 2026, Massey tunnel cost increase
Massey tunnel, revised completion2031Reportedmassey_doneGlobal News, Jul 6, 2026, Massey tunnel cost increase
Cancelled 10-lane bridge budget (2017)$3.5BReportedbridge_0Daily Hive, cancelled 10-lane bridge budget and lowest bid
Cancelled bridge, lowest bid (2017)$2.6BReportedbridge_bidDaily Hive, cancelled 10-lane bridge budget and lowest bid
Cancelled bridge, scheduled completion2022Reportedbridge_doneDaily Hive, cancelled 10-lane bridge budget and lowest bid
Broadway Subway at construction start (2021)$2.83BReportedbway_0Daily Hive, Dec 18, 2024, Broadway Subway and Pattullo Bridge cost updates
Broadway Subway, latest (Fall 2024)$2.95BReportedbway_1Daily Hive, Dec 18, 2024, Broadway Subway and Pattullo Bridge cost updates
Pattullo Bridge at construction start (2021)$1.38BReportedpatt_0Daily Hive, Dec 18, 2024, Broadway Subway and Pattullo Bridge cost updates
Pattullo Bridge, latest (Fall 2024)$1.64BReportedpatt_1Daily Hive, Dec 18, 2024, Broadway Subway and Pattullo Bridge cost updates
Richmond Hospital, business case (2020/21)$0.86BReportedrich_0Daily Hive, Jun 4, 2024, Richmond Hospital cost update
Richmond Hospital, latest (Jun 2024)$1.96BReportedrich_1Daily Hive, Jun 4, 2024, Richmond Hospital cost update
Cloverdale Hospital, 2021 estimate$1.66BReportedclov_0Daily Hive, Sep 12, 2023, Cloverdale hospital cost
Cloverdale Hospital, latest (Sep 2023)$2.88BReportedclov_1Daily Hive, Sep 12, 2023, Cloverdale hospital cost
Site C, first approved budget (2014)$8.8BReportedsitec_0Daily Hive, May 21, 2026, Site C final cost
Site C, final cost$16.0BReportedsitec_1Daily Hive, May 21, 2026, Site C final cost
North Shore wastewater plant, as first announced$0.7BReportednsw_0CBC News, North Shore Wastewater Treatment Plant cost-sharing decision
North Shore wastewater plant, March 2024 estimate$3.86BReportednsw_1CBC News, North Shore Wastewater Treatment Plant cost-sharing decision
North Shore household share of the overrun, per year for 30 years$590Reportednsw_hhCBC News, North Shore Wastewater Treatment Plant cost-sharing decision
Vancouver non-residential construction price index, Q4 2020 (2017=100)110.7Verifiedi17_q4_20Statistics Canada, The Daily, Jul 30, 2024, building construction price indexes (Vancouver non-residential)
Same index, Q2 2023136.2Verifiedi17_q2_23Statistics Canada, The Daily, Jul 30, 2024, building construction price indexes (Vancouver non-residential)
Same index, Q2 2024143.2Verifiedi17_q2_24Statistics Canada, The Daily, Jul 30, 2024, building construction price indexes (Vancouver non-residential)
Same index, Q3 2024 (rebased 2023=100)106.2Verifiedi23_q3_24Statistics Canada, The Daily, Oct 29, 2026, building construction price indexes (Vancouver non-residential)
Same index, Q3 2026 (2023=100)112.3Verifiedi23_q3_26Statistics Canada, The Daily, Oct 29, 2026, building construction price indexes (Vancouver non-residential)
Q3 2026 index on 2017 base (chained; slightly low)151.4Illustrative · est.i17_q3_26= i17_q2_24*i23_q3_26/i23_q3_24
Construction prices, Q4 2020 to Q3 202637%Illustrative · est.infl= (i17_q3_26/i17_q4_20-1)*100
Massey budget increase105%Illustrative · est.massey_up= (massey_1/massey_0-1)*100
Massey budget if only prices had changed$5.7BIllustrative · est.massey_infl= massey_0*i17_q3_26/i17_q4_20
Massey increase inflation does not explain$2.8BIllustrative · est.massey_gap= massey_1-massey_infl
Share of Massey increase explained by inflation35%Illustrative · est.massey_share= (massey_infl-massey_0)/(massey_1-massey_0)*100
Massey: change after construction inflation50%Illustrative · est.massey_real= (massey_1/massey_infl-1)*100
Broadway: change after construction inflation−19%Illustrative · est.bway_real= (bway_1/(bway_0*i17_q2_24/i17_q4_20)-1)*100
Pattullo: change after construction inflation−8%Illustrative · est.patt_real= (patt_1/(patt_0*i17_q2_24/i17_q4_20)-1)*100
Richmond Hospital: change after construction inflation76%Illustrative · est.rich_real= (rich_1/(rich_0*i17_q2_24/i17_q4_20)-1)*100
Cloverdale Hospital: change after construction inflation41%Illustrative · est.clov_real= (clov_1/(clov_0*i17_q2_23/i17_q4_20)-1)*100
North Shore plant: latest ÷ first budget5.5×Illustrative · est.nsw_x= nsw_1/nsw_0
2017 bridge budget in Q3 2026 prices$5.3BIllustrative · est.bridge_today= bridge_0*i17_q3_26/100
Delay vs the cancelled bridge's opening9Illustrative · est.delay= massey_done-bridge_done
Model default: yearly construction inflation from here4%Illustrativeyr_inflIstari model; the restart premium and yearly inflation are the reader's assumptions
A note from Istari

You read to the end, which is the job description. If your organization has a question like this sitting in its records, this is what the answer can look like, built from your own data, in weeks. Start the conversation.