Why do some B.C. projects cost double?
The usual answer is inflation. Inflation is real. Here is how much of the bill it actually explains.
Both are true. They answer different questions.
Construction prices rose about a third. After that inflation, how much did the Broadway Subway budget grow?
Start with the good news
- The Broadway Subway grew from $2.83BR5 to $2.95BR5, less than prices rose.
- The Pattullo Bridge is tracking at or below construction inflation too: −8%est.15 after inflation.
- Site C, for all its overruns, now runs. B.C. can finish big things, and Broadway and Pattullo show it can land them near budget. The question is when the price gets locked in.
Strip out inflation and the list reorders itself
Every project looks like a scandal. Massey is up 105%. Richmond Hospital more than doubled.
Projects signed before the 2021 price spike come in below inflation. Projects still being designed through it blew past it.
$8.5B − $5.7B = $2.8B inflation does not explainInflation explains about 35% of Massey's increase. No Vancouver index exists for tunnels, so we use the closest local one. Budgets usually include escalation to completion, so this method can understate inflation's share.
The pattern points at one lever: risk is cheapest to lock in early, and most expensive to carry through years of redesign. It shows up on household bills too. The North Shore wastewater plant went from $0.7BR6 to $3.86BR6, 5.5×est.6 the first figure. North Shore households now pay about $590R6 a year for 30 years toward it.
Your turn: the bridge, in today's dollars
The cancelled bridge had a $3.5BR7 budget in 2017. Its lowest bid was $2.6BR7. Move it to today's prices, then add what a restart costs. This leaves out what a switch writes off on the tunnel.
Two readings of the switch
Camp 1: the bridge is cheaper
In today's prices the 2017 bridge is about $5.3Best.71, well under the tunnel's $8.5B.
If they are right: a costed bridge business case lands under the tunnel budget.
Camp 2: switching is the expensive part
The projects that blew up were the ones redesigned through the price spike. A restart adds years of exactly that.
If they are right: the bridge's new budget, once published, lands near or above the tunnel's.
Bridge or tunnel matters less than how fast the choice locks in. The cheapest crossing is the one under a signed contract soonest.
We would change this read if a project redesigned after 2021 comes in at or below construction inflation.
What better looks like
- One dashboard: every major project's budget against its first approved baseline, adjusted for construction inflation, updated quarterly.
- Restart costs in the open: what B.C. has already spent on the tunnel, and what a switch writes off.
- A date to sign: when the bridge goes to contract.
Ask your MLA: "What has the tunnel cost so far, and what will a switch to a bridge write off?"
Sources and the data layer
- Statistics Canada, The Daily, Jul 30, 2024, building construction price indexes (Vancouver non-residential). www150.statcan.gc.ca · retrieved 2026-10-31
- Statistics Canada, The Daily, Oct 29, 2026, building construction price indexes (Vancouver non-residential). www150.statcan.gc.ca · retrieved 2026-10-31
- Daily Hive, Aug 18, 2021, Massey tunnel business case. dailyhive.com · retrieved 2026-10-31
- Global News, Jul 6, 2026, Massey tunnel cost increase. globalnews.ca · retrieved 2026-10-31
- Daily Hive, Dec 18, 2024, Broadway Subway and Pattullo Bridge cost updates. dailyhive.com · retrieved 2026-10-31
- CBC News, North Shore Wastewater Treatment Plant cost-sharing decision. amp.cbc.ca · retrieved 2026-10-31
- Daily Hive, cancelled 10-lane bridge budget and lowest bid. dailyhive.com · retrieved 2026-10-31
- Victoria News, "Incoming B.C. premier Doerkson says there will be no fall legislative session," Nov 16, 2026 (Massey bridge pledge; cabinet orders). vicnews.com · retrieved 2026-11-21
- Daily Hive, Jun 4, 2024, Richmond Hospital cost update. dailyhive.com · retrieved 2026-10-31
- Daily Hive, Sep 12, 2023, Cloverdale hospital cost. dailyhive.com · retrieved 2026-10-31
- Daily Hive, May 21, 2026, Site C final cost. dailyhive.com · retrieved 2026-10-31
- Istari model; the restart premium and yearly inflation are the reader's assumptions. istaristrategy.com · retrieved 2026-11-21
Open the data layer: every number on this page
| Figure | Value | Tag | Key | Source or formula |
|---|---|---|---|---|
| Massey tunnel, business case (Aug 2021) | $4.15B | Reported | massey_0 | Daily Hive, Aug 18, 2021, Massey tunnel business case |
| Massey tunnel, latest budget (Jul 2026) | $8.5B | Reported | massey_1 | Global News, Jul 6, 2026, Massey tunnel cost increase |
| Massey tunnel, revised completion | 2031 | Reported | massey_done | Global News, Jul 6, 2026, Massey tunnel cost increase |
| Cancelled 10-lane bridge budget (2017) | $3.5B | Reported | bridge_0 | Daily Hive, cancelled 10-lane bridge budget and lowest bid |
| Cancelled bridge, lowest bid (2017) | $2.6B | Reported | bridge_bid | Daily Hive, cancelled 10-lane bridge budget and lowest bid |
| Cancelled bridge, scheduled completion | 2022 | Reported | bridge_done | Daily Hive, cancelled 10-lane bridge budget and lowest bid |
| Broadway Subway at construction start (2021) | $2.83B | Reported | bway_0 | Daily Hive, Dec 18, 2024, Broadway Subway and Pattullo Bridge cost updates |
| Broadway Subway, latest (Fall 2024) | $2.95B | Reported | bway_1 | Daily Hive, Dec 18, 2024, Broadway Subway and Pattullo Bridge cost updates |
| Pattullo Bridge at construction start (2021) | $1.38B | Reported | patt_0 | Daily Hive, Dec 18, 2024, Broadway Subway and Pattullo Bridge cost updates |
| Pattullo Bridge, latest (Fall 2024) | $1.64B | Reported | patt_1 | Daily Hive, Dec 18, 2024, Broadway Subway and Pattullo Bridge cost updates |
| Richmond Hospital, business case (2020/21) | $0.86B | Reported | rich_0 | Daily Hive, Jun 4, 2024, Richmond Hospital cost update |
| Richmond Hospital, latest (Jun 2024) | $1.96B | Reported | rich_1 | Daily Hive, Jun 4, 2024, Richmond Hospital cost update |
| Cloverdale Hospital, 2021 estimate | $1.66B | Reported | clov_0 | Daily Hive, Sep 12, 2023, Cloverdale hospital cost |
| Cloverdale Hospital, latest (Sep 2023) | $2.88B | Reported | clov_1 | Daily Hive, Sep 12, 2023, Cloverdale hospital cost |
| Site C, first approved budget (2014) | $8.8B | Reported | sitec_0 | Daily Hive, May 21, 2026, Site C final cost |
| Site C, final cost | $16.0B | Reported | sitec_1 | Daily Hive, May 21, 2026, Site C final cost |
| North Shore wastewater plant, as first announced | $0.7B | Reported | nsw_0 | CBC News, North Shore Wastewater Treatment Plant cost-sharing decision |
| North Shore wastewater plant, March 2024 estimate | $3.86B | Reported | nsw_1 | CBC News, North Shore Wastewater Treatment Plant cost-sharing decision |
| North Shore household share of the overrun, per year for 30 years | $590 | Reported | nsw_hh | CBC News, North Shore Wastewater Treatment Plant cost-sharing decision |
| Vancouver non-residential construction price index, Q4 2020 (2017=100) | 110.7 | Verified | i17_q4_20 | Statistics Canada, The Daily, Jul 30, 2024, building construction price indexes (Vancouver non-residential) |
| Same index, Q2 2023 | 136.2 | Verified | i17_q2_23 | Statistics Canada, The Daily, Jul 30, 2024, building construction price indexes (Vancouver non-residential) |
| Same index, Q2 2024 | 143.2 | Verified | i17_q2_24 | Statistics Canada, The Daily, Jul 30, 2024, building construction price indexes (Vancouver non-residential) |
| Same index, Q3 2024 (rebased 2023=100) | 106.2 | Verified | i23_q3_24 | Statistics Canada, The Daily, Oct 29, 2026, building construction price indexes (Vancouver non-residential) |
| Same index, Q3 2026 (2023=100) | 112.3 | Verified | i23_q3_26 | Statistics Canada, The Daily, Oct 29, 2026, building construction price indexes (Vancouver non-residential) |
| Q3 2026 index on 2017 base (chained; slightly low) | 151.4 | Illustrative · est. | i17_q3_26 | = i17_q2_24*i23_q3_26/i23_q3_24 |
| Construction prices, Q4 2020 to Q3 2026 | 37% | Illustrative · est. | infl | = (i17_q3_26/i17_q4_20-1)*100 |
| Massey budget increase | 105% | Illustrative · est. | massey_up | = (massey_1/massey_0-1)*100 |
| Massey budget if only prices had changed | $5.7B | Illustrative · est. | massey_infl | = massey_0*i17_q3_26/i17_q4_20 |
| Massey increase inflation does not explain | $2.8B | Illustrative · est. | massey_gap | = massey_1-massey_infl |
| Share of Massey increase explained by inflation | 35% | Illustrative · est. | massey_share | = (massey_infl-massey_0)/(massey_1-massey_0)*100 |
| Massey: change after construction inflation | 50% | Illustrative · est. | massey_real | = (massey_1/massey_infl-1)*100 |
| Broadway: change after construction inflation | −19% | Illustrative · est. | bway_real | = (bway_1/(bway_0*i17_q2_24/i17_q4_20)-1)*100 |
| Pattullo: change after construction inflation | −8% | Illustrative · est. | patt_real | = (patt_1/(patt_0*i17_q2_24/i17_q4_20)-1)*100 |
| Richmond Hospital: change after construction inflation | 76% | Illustrative · est. | rich_real | = (rich_1/(rich_0*i17_q2_24/i17_q4_20)-1)*100 |
| Cloverdale Hospital: change after construction inflation | 41% | Illustrative · est. | clov_real | = (clov_1/(clov_0*i17_q2_23/i17_q4_20)-1)*100 |
| North Shore plant: latest ÷ first budget | 5.5× | Illustrative · est. | nsw_x | = nsw_1/nsw_0 |
| 2017 bridge budget in Q3 2026 prices | $5.3B | Illustrative · est. | bridge_today | = bridge_0*i17_q3_26/100 |
| Delay vs the cancelled bridge's opening | 9 | Illustrative · est. | delay | = massey_done-bridge_done |
| Model default: yearly construction inflation from here | 4% | Illustrative | yr_infl | Istari model; the restart premium and yearly inflation are the reader's assumptions |
You read to the end, which is the job description. If your organization has a question like this sitting in its records, this is what the answer can look like, built from your own data, in weeks. Start the conversation.